An air-cooled chiller condenser is blown by a fan to dissipate heat, and the causes of high-pressure failures are:

This results in poor heat dissipation from the condenser, i.e. the heat generated inside the refrigeration refrigerant cycle cannot be removed by the fan. So there is a high-pressure alarm.

Solution: Check and repair the fan and exclude dust and debris around the fan cover. After shutdown, clean with compressed air or water gun.

This causes the high-pressure refrigerant gas in the refrigerant system to condense improperly so that a large amount of gas accumulates and the machine sounds a high-pressure alarm.

Solution: By cleaning and decontaminating the condenser. Consult the manufacturer for guidance on the exact method.

What can be used to pressurize a chiller system before opening the system for a non-major repair select one?

This situation usually occurs in the new machine or compressor maintenance, the refrigeration system mixed with air, resulting in air can not be condensed and kept in the condenser, leading to a high-pressure alarm.

Solution: Open the air separation valve, exhaust port or condenser inlet/outlet to vent the air in the chiller.

The effect is similar to that caused by entering air. Too much refrigerant cannot be condensed into liquid form, occupying too much condensing pipe area, reducing the condensing effect and thus increasing the pressure.

Solution: Slowly discharge some refrigerant at the low-pressure side.

What can be used to pressurize a chiller system before opening the system for a non-major repair select one?

The expansion valve is used to throttle the high-pressure liquid refrigerant into a vapor state. If the opening is too small, the pressure in the front side of the condenser will be too high.

Solution: Increase the opening of the expansion valve appropriately.

What can be used to pressurize a chiller system before opening the system for a non-major repair select one?

When a water-cooled chiller has a high-pressure alarm, it is mainly related to the cooling water system:

The water-cooled unit is supplied with circulating cooling water by a cooling water tower. If you forget to open the cooling water valve when you are using it, the cooling water cannot be circulated and supplied to the chiller.

Solution: Open the cooling water valve.

What can be used to pressurize a chiller system before opening the system for a non-major repair select one?

Both of these conditions lead to poor heat dissipation, the temperature of the refrigerant cannot be cooled down, and a high-pressure alarm will occur.

Solution: Check whether the size of the piping installed matches the size of the chiller, whether the pump is working properly, or whether the water valve is open to the maximum position.

What can be used to pressurize a chiller system before opening the system for a non-major repair select one?

A high-pressure alarm occurs when the cooling tower fails and the cooling water cannot be circulated and supplied to the chiller.

Solution: Check whether the cooling tower is defective.

Water-cooled chillers used for a long time without maintenance will easily lead to the accumulation of scale and other debris on the tube wall, which will inevitably affect the effectiveness of the condenser.

Solution: Hire a professional descaling company to remove water scale.

What can be used to pressurize a chiller system before opening the system for a non-major repair select one?

The effect is similar to that caused by entering air. Too much refrigerant cannot be condensed into liquid form, occupying too much condensing pipe area, reducing the condensing effect and thus increasing the pressure.

Solution: Slowly discharge some refrigerant at the low-pressure side.

The expansion valve is used to throttle the high-pressure liquid refrigerant into a vapor state. If the opening is too small, the pressure on the front side of the condenser will be too high.

Solution: Increase the opening of the expansion valve appropriately.

Also looking for low-pressure alarm troubleshooting? Check this.

Leave your comment to support us!

What can be used to pressurize a chiller system before opening the system for a non-major repair select one?

Expert specializing in industrial chiller machines for more than 10 years, good at water cooling solutions in the energy, aerospace, automotive, electronics, manufacture processing, medical industries etc.

This website requires certain cookies to work and uses other cookies to help you have the best experience. By visiting this website, certain cookies have already been set, which you may delete and block. By closing this message or continuing to use our site, you agree to the use of cookies. Visit our updated privacy and cookie policy to learn more.

This Website Uses Cookies
By closing this message or continuing to use our site, you agree to our cookie policy. Learn More This website requires certain cookies to work and uses other cookies to help you have the best experience. By visiting this website, certain cookies have already been set, which you may delete and block. By closing this message or continuing to use our site, you agree to the use of cookies. Visit our updated privacy and cookie policy to learn more.

What type of equipment can be worked on with Type III certification?A High pressureB Medium pressureC Low pressure

D Vacuum pressure

When installing more than one pressure relief valves must be installed;A in series.B in parallel C in the suction line

D on top of compressor head

The owner must keep records of refrigerant added during service and maintenance on equipment;A with charges of 25 lbs or greater.B with charges of 50 lbs or greater.C with charges of 100 lbs or greater.D with charges of 150 lbs or greater.

B with charges of 50 lbs or greater.

After all the liquid has been removed from an average 350 ton approximately how much vapor refrigerant remains in the system?A 100lbsB 150lbsC 350lbs

D 45lbs

When charging a system with a low pressure refrigerant should be introduced as a vapor to raise saturation temperature to a minim of;A 0 degreesB 36 degreesC 40 degrees

D 70 degrees

Where is the purge unit located in a low-pressure system?A The top of the condenserB In the lowest location.C Above the shellD Before the oil separator.

A The top of the condenser

In a chiller air and other noncondensables collect;A at the bottom of the compressor.B at the top section of the condenser.C at the bottom of the evaporator.

D at the header before the metering device.

B at the top section of the condenser.

A rupture disk for low pressure chiller will rupture at;A 5 psigB 10 psigC 15 psig

D 20 psig

The Standard for machine room safety is;A ASHRAE-15B ASHRAE-34C ARI-740

D EPA-740

Who establishes the refrigerant safety group standard.A)ARIB)ULC)ASHRAE

D)ASE

A low pressure chiller used for comfort cooling must be repaired if it has an annual leak rate of ____ of the total charge.A)15 percentB)20 percentC)30 percentD)50 percent

ASHRAE 34 Standard Safety classifies R-134a as;A)A1B)A2C)B1

D)B2

Because a low-pressure system operates below atmospheric pressure (in a vacuum),A)the system is unlikely to have air and moisture to enter the system.B)leaks in the gaskets or fittings will cause air and moisture to enter the system.C)leaks in the gaskets or fittings will cause substantial refrigeramt leaks.

D)leaks in the gaskets or fittings will cause oil clogging at the condenser.

B)leaks in the gaskets or fittings will cause air and moisture to enter the system.

To repair a chiller operating with R-22 the technician;A)does not need a certification.B)must have a Type I certification.C)must have a Type III certification.

D)must have a Type II certification.

D)must have a Type II certification.

Which of the following refrigerants has a safety classification of B-1A)CFC 12 (R-12)B)HFC 134A (R134A)C)HCFC 123 (R-123)

D)CFC 11 (R-11)

During evacuation of systems with large amounts of water, it may be necessary to;A)increase pressure by introducing nitrogen to counteract freezing.B)purge the condenser.C)drain the compressor.

D)decrease pressure by introducing nitrogen to counteract freezing.

A)increase pressure by introducing nitrogen to counteract freezing.

When leak testing a low pressure chiller, the maximum pressure to use is;A)5 psig.B)10 psig.C)15 psig.

D)20 psig.

The most efficient method of leak checking a charged low-pressure refrigeration unit is toA pressurize the system by the use of controlled hot water or heater blankets.B pull a 500 micron vacuum and hold for about 12 minutes to see if it rises to 1,500 micron.C pull to 20 inch vacuum and hold for about 24 hours without more than a 2 inch rise in pressure.

D pull to 29.9 inch vacuum and hold for about 24 hours without more than a 2 inch rise in pressure.

A pressurize the system by the use of controlled hot water or heater blankets.

When pressurizing a system, do not exceedA 5 psigB 10 psigC 15 psig

D 20psig

After reaching the required vacuum on an appliance when servicing, moisture is indicated by;A complete rise from the vacuum to a positive pressure.B multiple rises in pressure over a period of time with increase of pauses between rises.C slow rises in pressure, and then a reduction of pressure over a period of time.

D a 500 micron measurement in the system at the shortest point to the vacuum pump.

B multiple rises in pressure over a period of time with increase of pauses between rises.

EPA required evacuation levels for recovery or recycling equipment manufactured or imported before Nov. 15, 1993 isA 15 inches HgB 20 inches HgC 25 inches of Hg

D 30 inches Hg

EPA required evacuation levels for recovery or recycling equipment manufactured or imported on or after Nov. 15, 1993 isA 10 mm Hg absoluteB 15 mm Hg absoluteC 20 mm Hg absolute

D 25 mm Hg absolute

What can be used to pressurize a chiller system before opening the system for a non-major repair?A Controlled hot waterB nitrogenC refrigerant 409

D compressed air

Refrigerant recovery from a system using R-11 or R-123 starts withA vapor removal and is followed by liquid recovery.B liquid removal and is followed by vapor recovery.C alternating between liquid and vapor phase of recovery.

D operating the compressor.

B liquid removal and is followed by vapor recovery.

If a strong odor is detected during the recovery process,A the refrigerant is most likely R717 (Amonia)B the purge unit has activatedC a compressor burn-out may have occurredD it is a good indicator that R123 is the refrigerant being recovered

C a compressor burn-out may have occurred